"Ohio’s Davis-Besse nuclear plant is scheduled to close within three years, but decommissioning could take up to 60 years, and after that a regulated radioactive fuel storage facility will remain on the site indefinitely.
FirstEnergy’s generation subsidiaries announced plans to shut down Davis-Besse and two other nuclear plants three days before filing for bankruptcy in March. Dealing with radioactive fuel and waste, decontamination and demolition will take decades.
Inspectors and analysts for the Nuclear Regulatory Commission outlined the process at a public meeting last month in nearby Port Clinton, Ohio. Officials with FirstEnergy Solutions and the Environmental Law & Policy Center also attended. Here are some of the questions they answered:"
Kathiann M. Kowalski reports for Midwest Energy News July 12, 2018.