"North Carolina regulators have cited five more Duke Energy power plants for lacking required storm water permits after a massive spill at one of the company’s coal ash dumps coated 70 miles of the Dan River in toxic sludge."
"The state department of environment and natural resources announced Monday that Charlotte-based Duke had been issued formal notices of violation for not having the needed permits, which are required to legally discharge rainwater draining from its plants into public waterways.
Two other violations were issued Friday against the Dan River Steam Station in Eden, site of the 2 February spill. The company could face hundreds of thousands of dollars in fines for the violations.
State regulators indicated they had been aware since at least 2011 that some Duke facilities lacked the required storm water permits, yet took no enforcement action until after last month’s disaster."
The Associated Press had the story March 3, 2014.
"North Carolina Cites Five More Power Plants in Massive Coal Ash Spill"
Source: AP, 03/04/2014