Cookie Control

This site uses cookies to store information on your computer.

Some cookies on this site are essential, and the site won't work as expected without them. These cookies are set when you submit a form, login or interact with the site by doing something that goes beyond clicking on simple links.

We also use some non-essential cookies to anonymously track visitors or enhance your experience of the site. If you're not happy with this, we won't set these cookies but some nice features of the site may be unavailable.

By using our site you accept the terms of our Privacy Policy.

(One cookie will be set to store your preference)
(Ticking this sets a cookie to hide this popup if you then hit close. This will not store any personal information)

"U.S. Judge Orders Oil-Spill Response Plan For Dakota Access Pipeline"

"WASHINGTON - A federal judge ordered Energy Transfer Partners LP to coordinate with local tribes and the Army Corps of Engineers to create an oil-spill response plan for the controversial Dakota Access Pipeline by next April, a decision he said will allow oil to keep flowing and prevent spills.

The order on Monday by U.S. District Judge James Boasberg came nearly six months after he ruled that the Army Corps of Engineers review of the project, which transports oil from North Dakota near Native American reservations to Illinois, was inadequate before it granted federal permits.

In October the judge ruled that crude oil can continue to flow through the 1,170-mile (1,900-km) North Dakota-to-Illinois pipeline while the review is conducted. It has shipped crude since June."

Valerie Volcovici reports for Reuters December 4, 2017.

Source: Reuters, 12/05/2017