Cookie Control

This site uses cookies to store information on your computer.

Some cookies on this site are essential, and the site won't work as expected without them. These cookies are set when you submit a form, login or interact with the site by doing something that goes beyond clicking on simple links.

We also use some non-essential cookies to anonymously track visitors or enhance your experience of the site. If you're not happy with this, we won't set these cookies but some nice features of the site may be unavailable.

By using our site you accept the terms of our Privacy Policy.

(One cookie will be set to store your preference)
(Ticking this sets a cookie to hide this popup if you then hit close. This will not store any personal information)

"Brazil Approves Massive Amazon Dam For Construction"

"Brazil's environment agency gave its definitive approval on Wednesday for construction of the Belo Monte hydroelectric dam, a controversial $17 billion project in the Amazon that has drawn criticism from native Indians and conservationists.

The regulator, Ibama, issued licenses to the consortium in charge of Belo Monte to build the massive dam on the Xingu River, a tributary to the Amazon.

The government has said the 11,200-megawatt project, due to start producing electricity in 2015, is crucial to provide power to Brazil's fast-growing economy. It will be the world's third biggest hydroelectric dam after China's Three Gorges and Itaipu on the border of Brazil and Paraguay.

In January, Ibama had issued a preliminary license allowing the construction site to be set up.

Since then the project has been halted and resumed several times due to court injunctions obtained by environmentalists and native Indians opposing the dam."

Leonardo Goy and Raymond Colitt report for Reuters June 2, 2011.

Source: Reuters, 06/02/2011