"SPRING CITY, Tenn. — When the Tennessee Valley Authority first ordered Watts Bar 2, the nuclear reactor now approaching completion here, demand for electricity was growing at 7 percent a year and coal supplies were uncertain. The mercury, soot and acid rain that coal produced were simply accepted as the way things were, and many of the people who now worry about global warming had not yet been born.
But that was 1970. Today nearly all of that is reversed as Watts Bar 2, the nuclear industry’s version of a time traveler, prepares to begin operations. Now there is barely any growth in electricity demand, and plenty of coal, but most aging coal-burning plants need expensive cleaning or replacement. Thus the reactor, the T.V.A. reasons, is arriving at an opportune moment, even if almost every projection made over the last 44 years has proved wrong. With halting progress amid changing projections, construction has taken longer than that for the Panama Canal or the Great Pyramid of Cheops. ...
The agency started Watts Bar as part of a campaign to build 17 reactors, but dropped the project in 1988 after spending about $1.7 billion, when it was supposedly 80 percent complete. In 2007, with electricity demand growing again, the T.V.A. board voted to restart work because, consultants said, it could be finished for $2 billion. But by the end of next year, when commercial operation is now expected, the T.V.A. will have spent more than $4 billion."
Matthew L. Wald reports for the New York Times October 19, 2014.
In Tennessee, Time Comes for a Nuclear Plant 4 Decades in the Making
Source: NY Times, 10/20/2014